Commissioning readiness

Testing & commissioning

Protection, metering, OLTE, CEIG approval, line testing, ABT metering and charging.

8 recordsNot started: 8
#ItemTarget dateScopeDoneTest / approval ref.Depends onStatus
1OPGW (Optical ground wire) — Erection15.11.202616.5 Mtr0——Not started
2OLTE (Optical line terminal Equipments) — Erection20.11.20262 Nos0——Not started
3Relay Distance protection — Erection20.11.20262 Nos0——Not started
4Metering CT & PT — Erection20.11.20264 Set0——Not started
5Electrical safety clearance — CEIG Approval25.11.20261 Lot0——Not started
6132KV Line testing & Commissioning25.11.20261 Lot0——Not started
7ABT Meter — Erection30.11.20263 Nos0——Not started
8132KV Line Charging & EHT Connection30.11.20261 No0——Not started