Commissioning readiness
Testing & commissioning
Protection, metering, OLTE, CEIG approval, line testing, ABT metering and charging.
8 recordsNot started: 8
| # | Item | Target date | Scope | Done | Test / approval ref. | Depends on | Status |
|---|---|---|---|---|---|---|---|
| 1 | OPGW (Optical ground wire) — Erection | 15.11.2026 | 16.5 Mtr | 0 | — | — | Not started |
| 2 | OLTE (Optical line terminal Equipments) — Erection | 20.11.2026 | 2 Nos | 0 | — | — | Not started |
| 3 | Relay Distance protection — Erection | 20.11.2026 | 2 Nos | 0 | — | — | Not started |
| 4 | Metering CT & PT — Erection | 20.11.2026 | 4 Set | 0 | — | — | Not started |
| 5 | Electrical safety clearance — CEIG Approval | 25.11.2026 | 1 Lot | 0 | — | — | Not started |
| 6 | 132KV Line testing & Commissioning | 25.11.2026 | 1 Lot | 0 | — | — | Not started |
| 7 | ABT Meter — Erection | 30.11.2026 | 3 Nos | 0 | — | — | Not started |
| 8 | 132KV Line Charging & EHT Connection | 30.11.2026 | 1 No | 0 | — | — | Not started |