Schedule health

Delay & risk analysis

Rule-based flags as of 12.10.2026: Overdue = target date passed with balance remaining; At risk = due within 21 days and under 50% done.

ActivityTargetDone / Scope%DaysStatus
Tower — Erection31.10.20260/34 Nos019At risk
Cable Joints — End termination31.10.20260/10 Nos019At risk
Panther Conductor — Stringing31.10.20260/8.5 KM019At risk
Cable trench — Excavation20.10.20265.5/8.0 KM698In progress
Cable — Laying31.10.20264.0/8.0 KM5019In progress
OPGW (Optical ground wire) — Erection15.11.20260/16.5 Mtr034Not started
OLTE (Optical line terminal Equipments) — Erection20.11.20260/2 Nos039Not started
Relay Distance protection — Erection20.11.20260/2 Nos039Not started
Metering CT & PT — Erection20.11.20260/4 Set039Not started
Electrical safety clearance — CEIG Approval25.11.20260/1 Lot044Not started
132KV Line testing & Commissioning25.11.20260/1 Lot044Not started
ABT Meter — Erection30.11.20260/3 Nos049Not started
132KV Line Charging & EHT Connection30.11.20260/1 No049Not started
Tower Pit — Excavation25.09.202634/34 Nos100—Complete
Tower STUBS — Casting & Foundation27.09.202634/34 Nos100—Complete

AI risk review & look-ahead

Uses only the activity table and daily entries — no invented figures.