Schedule health
Delay & risk analysis
Rule-based flags as of 12.10.2026: Overdue = target date passed with balance remaining; At risk = due within 21 days and under 50% done.
| Activity | Target | Done / Scope | % | Days | Status |
|---|---|---|---|---|---|
| Tower — Erection | 31.10.2026 | 0/34 Nos | 0 | 19 | At risk |
| Cable Joints — End termination | 31.10.2026 | 0/10 Nos | 0 | 19 | At risk |
| Panther Conductor — Stringing | 31.10.2026 | 0/8.5 KM | 0 | 19 | At risk |
| Cable trench — Excavation | 20.10.2026 | 5.5/8.0 KM | 69 | 8 | In progress |
| Cable — Laying | 31.10.2026 | 4.0/8.0 KM | 50 | 19 | In progress |
| OPGW (Optical ground wire) — Erection | 15.11.2026 | 0/16.5 Mtr | 0 | 34 | Not started |
| OLTE (Optical line terminal Equipments) — Erection | 20.11.2026 | 0/2 Nos | 0 | 39 | Not started |
| Relay Distance protection — Erection | 20.11.2026 | 0/2 Nos | 0 | 39 | Not started |
| Metering CT & PT — Erection | 20.11.2026 | 0/4 Set | 0 | 39 | Not started |
| Electrical safety clearance — CEIG Approval | 25.11.2026 | 0/1 Lot | 0 | 44 | Not started |
| 132KV Line testing & Commissioning | 25.11.2026 | 0/1 Lot | 0 | 44 | Not started |
| ABT Meter — Erection | 30.11.2026 | 0/3 Nos | 0 | 49 | Not started |
| 132KV Line Charging & EHT Connection | 30.11.2026 | 0/1 No | 0 | 49 | Not started |
| Tower Pit — Excavation | 25.09.2026 | 34/34 Nos | 100 | — | Complete |
| Tower STUBS — Casting & Foundation | 27.09.2026 | 34/34 Nos | 100 | — | Complete |
AI risk review & look-ahead
Uses only the activity table and daily entries — no invented figures.