P1 – JSM IU 132 kV Line
Weighted verified progress
Not published — 15 activities missing scope/verified/weight; weights total 0%
- Tower pit excavationref 34 Nos
- Tower foundation & stub castingref 34 Nos
- Tower erectionref 0 Nos
- Panther conductor stringingref 0 km
- OPGW erectionref 0 km
- UG cable trench excavationref 5.5 km
- UG cable layingref 4.0 km
- Cable joints & end terminationref 0 Nos
- OLTE installationref 0 Nos
- Relay distance protectionref 0 Nos
- Metering CT/PTref 0 Set
- Electrical safety clearance & CEIG approvalref 0 Lot
- Line testing & commissioningref 0 Lot
- ABT meter erectionref 0 Nos
- Line charging & EHT connectionref 0 Lot
P2 – RVPN Parewar GSS 132 kV Line
Weighted verified progress
Not published — 6 activities missing scope/verified/weight; weights total 0%
- Tower excavationref 67 Nos
- Foundation & stubsref 67 Nos
- Tower erectionref 67 Nos
- Conductor stringingref 0 Nos
- Line-route progress—
- Work-package completion evidence—
P3 – JK Cement 132 kV Bay at RVPN GSS
Weighted verified progress
Not published — 8 activities missing scope/verified/weight; weights total 0%
- Civil foundation—
- Electrical structures—
- Equipment erection—
- Earthing & electrical connections—
- Protection & metering—
- Inspection & testing—
- Statutory approvals—
- Commissioning readiness—
Packages are never combined into one unweighted percentage. Dashed bars = no verified quantity yet (imported reference only).
WBS · verified progress
Work packages
Three independent packages. Progress uses verified quantities only — imported slide figures are shown separately and never counted as certified achievement.
Balance = Approved scope − Verified cumulative. Progress % = Verified ÷ Scope × 100. Schedule variance = Progress % − Planned %. A weighted package % is shown only when every activity has scope, a verified value and weights total 100%.
| # | Package | Activity ID | Activity | Unit | Approved scope | Imported (unverified) | Verified cumulative | Planned % to date | Approved weight % | Contractor | Engineer | Status | Source |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | P1 – JSM IU 132 kV Line | P1-01 | Tower pit excavation | Nos | 34 | 34 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 2 | P1 – JSM IU 132 kV Line | P1-02 | Tower foundation & stub casting | Nos | 34 | 34 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 3 | P1 – JSM IU 132 kV Line | P1-03 | Tower erection | Nos | 34 | 0 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 4 | P1 – JSM IU 132 kV Line | P1-04 | Panther conductor stringing | km | 8.5 | 0 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 5 | P1 – JSM IU 132 kV Line | P1-05 | OPGW erection | km | 16.5 | 0 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 6 | P1 – JSM IU 132 kV Line | P1-06 | UG cable trench excavation | km | 8.0 | 5.5 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 7 | P1 – JSM IU 132 kV Line | P1-07 | UG cable laying | km | 8.0 | 4.0 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 8 | P1 – JSM IU 132 kV Line | P1-08 | Cable joints & end termination | Nos | 10 | 0 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 9 | P1 – JSM IU 132 kV Line | P1-09 | OLTE installation | Nos | 2 | 0 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 10 | P1 – JSM IU 132 kV Line | P1-10 | Relay distance protection | Nos | 2 | 0 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 11 | P1 – JSM IU 132 kV Line | P1-11 | Metering CT/PT | Set | 4 | 0 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 12 | P1 – JSM IU 132 kV Line | P1-12 | Electrical safety clearance & CEIG approval | Lot | 1 | 0 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 13 | P1 – JSM IU 132 kV Line | P1-13 | Line testing & commissioning | Lot | 1 | 0 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 14 | P1 – JSM IU 132 kV Line | P1-14 | ABT meter erection | Nos | 3 | 0 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 15 | P1 – JSM IU 132 kV Line | P1-15 | Line charging & EHT connection | Lot | 1 | 0 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 16 No approved scope | P2 – RVPN Parewar GSS 132 kV Line | P2-01 | Tower excavation | Nos | — | 67 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 17 No approved scope | P2 – RVPN Parewar GSS 132 kV Line | P2-02 | Foundation & stubs | Nos | — | 67 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 18 No approved scope | P2 – RVPN Parewar GSS 132 kV Line | P2-03 | Tower erection | Nos | — | 67 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 19 No approved scope | P2 – RVPN Parewar GSS 132 kV Line | P2-04 | Conductor stringing | Nos | — | 0 | — | — | — | — | — | Reference – unverified | Oct 2026 slide (imported reference) |
| 20 No unit of measurement · No approved scope | P2 – RVPN Parewar GSS 132 kV Line | P2-05 | Line-route progress | — | — | — | — | — | — | — | — | Not started | — |
| 21 No approved scope | P2 – RVPN Parewar GSS 132 kV Line | P2-06 | Work-package completion evidence | Lot | — | — | — | — | — | — | — | Not started | — |
| 22 No unit of measurement · No approved scope | P3 – JK Cement 132 kV Bay at RVPN GSS | P3-01 | Civil foundation | — | — | — | — | — | — | — | — | Not started | — |
| 23 No unit of measurement · No approved scope | P3 – JK Cement 132 kV Bay at RVPN GSS | P3-02 | Electrical structures | — | — | — | — | — | — | — | — | Not started | — |
| 24 No unit of measurement · No approved scope | P3 – JK Cement 132 kV Bay at RVPN GSS | P3-03 | Equipment erection | — | — | — | — | — | — | — | — | Not started | — |
| 25 No unit of measurement · No approved scope | P3 – JK Cement 132 kV Bay at RVPN GSS | P3-04 | Earthing & electrical connections | — | — | — | — | — | — | — | — | Not started | — |
| 26 No unit of measurement · No approved scope | P3 – JK Cement 132 kV Bay at RVPN GSS | P3-05 | Protection & metering | — | — | — | — | — | — | — | — | Not started | — |
| 27 No unit of measurement · No approved scope | P3 – JK Cement 132 kV Bay at RVPN GSS | P3-06 | Inspection & testing | — | — | — | — | — | — | — | — | Not started | — |
| 28 No unit of measurement · No approved scope | P3 – JK Cement 132 kV Bay at RVPN GSS | P3-07 | Statutory approvals | — | — | — | — | — | — | — | — | Not started | — |
| 29 No unit of measurement · No approved scope | P3 – JK Cement 132 kV Bay at RVPN GSS | P3-08 | Commissioning readiness | — | — | — | — | — | — | — | — | Not started | — |