P1 – JSM IU 132 kV Line

Weighted verified progress

Not published — 15 activities missing scope/verified/weight; weights total 0%

  • Tower pit excavationref 34 Nos
  • Tower foundation & stub castingref 34 Nos
  • Tower erectionref 0 Nos
  • Panther conductor stringingref 0 km
  • OPGW erectionref 0 km
  • UG cable trench excavationref 5.5 km
  • UG cable layingref 4.0 km
  • Cable joints & end terminationref 0 Nos
  • OLTE installationref 0 Nos
  • Relay distance protectionref 0 Nos
  • Metering CT/PTref 0 Set
  • Electrical safety clearance & CEIG approvalref 0 Lot
  • Line testing & commissioningref 0 Lot
  • ABT meter erectionref 0 Nos
  • Line charging & EHT connectionref 0 Lot

P2 – RVPN Parewar GSS 132 kV Line

Weighted verified progress

Not published — 6 activities missing scope/verified/weight; weights total 0%

  • Tower excavationref 67 Nos
  • Foundation & stubsref 67 Nos
  • Tower erectionref 67 Nos
  • Conductor stringingref 0 Nos
  • Line-route progress—
  • Work-package completion evidence—

P3 – JK Cement 132 kV Bay at RVPN GSS

Weighted verified progress

Not published — 8 activities missing scope/verified/weight; weights total 0%

  • Civil foundation—
  • Electrical structures—
  • Equipment erection—
  • Earthing & electrical connections—
  • Protection & metering—
  • Inspection & testing—
  • Statutory approvals—
  • Commissioning readiness—

Packages are never combined into one unweighted percentage. Dashed bars = no verified quantity yet (imported reference only).

WBS · verified progress

Work packages

Three independent packages. Progress uses verified quantities only — imported slide figures are shown separately and never counted as certified achievement.

Balance = Approved scope − Verified cumulative. Progress % = Verified ÷ Scope × 100. Schedule variance = Progress % − Planned %. A weighted package % is shown only when every activity has scope, a verified value and weights total 100%.

29 recordsNot started: 10Reference – unverified: 1914 flagged
#PackageActivity IDActivityUnitApproved scopeImported (unverified)Verified cumulativePlanned % to dateApproved weight %ContractorEngineerStatusSource
1P1 – JSM IU 132 kV LineP1-01Tower pit excavationNos3434—————Reference – unverifiedOct 2026 slide (imported reference)
2P1 – JSM IU 132 kV LineP1-02Tower foundation & stub castingNos3434—————Reference – unverifiedOct 2026 slide (imported reference)
3P1 – JSM IU 132 kV LineP1-03Tower erectionNos340—————Reference – unverifiedOct 2026 slide (imported reference)
4P1 – JSM IU 132 kV LineP1-04Panther conductor stringingkm8.50—————Reference – unverifiedOct 2026 slide (imported reference)
5P1 – JSM IU 132 kV LineP1-05OPGW erectionkm16.50—————Reference – unverifiedOct 2026 slide (imported reference)
6P1 – JSM IU 132 kV LineP1-06UG cable trench excavationkm8.05.5—————Reference – unverifiedOct 2026 slide (imported reference)
7P1 – JSM IU 132 kV LineP1-07UG cable layingkm8.04.0—————Reference – unverifiedOct 2026 slide (imported reference)
8P1 – JSM IU 132 kV LineP1-08Cable joints & end terminationNos100—————Reference – unverifiedOct 2026 slide (imported reference)
9P1 – JSM IU 132 kV LineP1-09OLTE installationNos20—————Reference – unverifiedOct 2026 slide (imported reference)
10P1 – JSM IU 132 kV LineP1-10Relay distance protectionNos20—————Reference – unverifiedOct 2026 slide (imported reference)
11P1 – JSM IU 132 kV LineP1-11Metering CT/PTSet40—————Reference – unverifiedOct 2026 slide (imported reference)
12P1 – JSM IU 132 kV LineP1-12Electrical safety clearance & CEIG approvalLot10—————Reference – unverifiedOct 2026 slide (imported reference)
13P1 – JSM IU 132 kV LineP1-13Line testing & commissioningLot10—————Reference – unverifiedOct 2026 slide (imported reference)
14P1 – JSM IU 132 kV LineP1-14ABT meter erectionNos30—————Reference – unverifiedOct 2026 slide (imported reference)
15P1 – JSM IU 132 kV LineP1-15Line charging & EHT connectionLot10—————Reference – unverifiedOct 2026 slide (imported reference)
16
No approved scope
P2 – RVPN Parewar GSS 132 kV LineP2-01Tower excavationNos—67—————Reference – unverifiedOct 2026 slide (imported reference)
17
No approved scope
P2 – RVPN Parewar GSS 132 kV LineP2-02Foundation & stubsNos—67—————Reference – unverifiedOct 2026 slide (imported reference)
18
No approved scope
P2 – RVPN Parewar GSS 132 kV LineP2-03Tower erectionNos—67—————Reference – unverifiedOct 2026 slide (imported reference)
19
No approved scope
P2 – RVPN Parewar GSS 132 kV LineP2-04Conductor stringingNos—0—————Reference – unverifiedOct 2026 slide (imported reference)
20
No unit of measurement · No approved scope
P2 – RVPN Parewar GSS 132 kV LineP2-05Line-route progress————————Not started—
21
No approved scope
P2 – RVPN Parewar GSS 132 kV LineP2-06Work-package completion evidenceLot———————Not started—
22
No unit of measurement · No approved scope
P3 – JK Cement 132 kV Bay at RVPN GSSP3-01Civil foundation————————Not started—
23
No unit of measurement · No approved scope
P3 – JK Cement 132 kV Bay at RVPN GSSP3-02Electrical structures————————Not started—
24
No unit of measurement · No approved scope
P3 – JK Cement 132 kV Bay at RVPN GSSP3-03Equipment erection————————Not started—
25
No unit of measurement · No approved scope
P3 – JK Cement 132 kV Bay at RVPN GSSP3-04Earthing & electrical connections————————Not started—
26
No unit of measurement · No approved scope
P3 – JK Cement 132 kV Bay at RVPN GSSP3-05Protection & metering————————Not started—
27
No unit of measurement · No approved scope
P3 – JK Cement 132 kV Bay at RVPN GSSP3-06Inspection & testing————————Not started—
28
No unit of measurement · No approved scope
P3 – JK Cement 132 kV Bay at RVPN GSSP3-07Statutory approvals————————Not started—
29
No unit of measurement · No approved scope
P3 – JK Cement 132 kV Bay at RVPN GSSP3-08Commissioning readiness————————Not started—