Next 7 days
Look-ahead planning
Activity plan for the coming week with resources, permits, dependencies and risks.
Plans exceeding remaining scope are flagged automatically.
3 recordsNot started: 3
| # | Activity | Location / tower | Contractor | Start | Finish | Planned qty | Unit | Manpower | Material | Permit | Risk / mitigation | Status |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Tower erection | — | — | — | — | 3 | Nos | — | — | — | Slide next-week target — planning input only | Not started |
| 2 | UG trench excavation | — | — | — | — | 1.0 | KM | — | — | — | Slide next-week target — planning input only | Not started |
| 3 | UG cable laying | — | — | — | — | 1.0 | KM | — | — | — | Slide next-week target — planning input only | Not started |